Agenda item

OSD Property Safety Inspections Progress Update

Minutes:

The Responsive Repairs Manager provided an update on the progress of implementing the recommendations in the Limited Assurance audit report on ‘OSD Property Safety Inspections’ issued on 16 May, 2018.

 

The committee considered a detailed implementation schedule that listed the actions that had been taken against each recommendation.  Examples were provided of the work that had already been undertaken and members were satisfied the recommendations had been implemented.

 

The Committee thanked the Responsive Repairs Manager for attending.

 

* RESOLVED –

 

That the updates be noted.

 