Decision details
Sheltered Housing Investment Update
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Decision:
*RESOLVED –
1. That the refurbishment project at Leander Court, in conjunction with the previously approved works at Mallard Court and Pullman Close, Staveley, be completed at an estimated cost of £3.9 million.
2. That the temporary closure and refurbishment of Aston Court, Staveley, be approved at an estimated cost of £3.2 million.
3. That lettings at Mallard and Leander Courts be ceased to enable a suitable decant strategy to be undertaken using accommodation at Aston Court.
REASON FOR DECISIONS
To meet the Council’s priority ‘to improve the quality of life for local people’ and objective five ‘to increase the supply and quality of housing in Chesterfield Borough to meet current and future needs.’
Reason Key: Decision to spend £100,000 or more from an approved budget;
Wards Affected: (All Wards);
Contact: Vanessa Watson, Asset management and programmed works manager Email: vanessa.watson@chesterfield.gov.uk Tel: 01246 345135.
Report author: Vanessa Watson
Publication date: 17/12/2019
Date of decision: 17/12/2019
Decided at meeting: 17/12/2019 - Cabinet