Housing Capital Programme: 2020/21 to 2024/25

Minutes:

Pursuant to Cabinet Minute No. 114 the Assistant Director – Housing submitted the Housing (Public Sector) Capital Programme for 2019/20 and 2020/21 and the provisional Capital Programmes for 2021/22 to 2024/25 for approval.

 

RESOLVED –   

 

1.   That the Housing (Public Sector) revised Capital Programme for 2019/20 be approved.

 

2.   That the Housing (Public Sector) Capital Programmes for 2020/21 be approved and its procurement, as necessary, be authorised.

 

3.   That the Housing (Public Sector) Capital programmes for 2021/22 to 2024/25 be provisionally approved.

 

4.   That the commercial services share of the 2020/21 programme be approved.

 

5.   That delegated authority be granted to the Assistant Director - Housing and/or the Acting Chief Finance Officer to transfer funds between programme heads and budgets in order to manage the Capital Programme as set out in the officers’ report.