Decision details

UKSPF Programme Delivery

Decision Maker: Service Director - Economic Growth

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To enable effective delivery of projects in line with the investment plan.

Decision:

To approve UKSPF16a Heritage Interpretation Plan Project.

To approve the proposed amendments to the grant funding guidance for UKSPF13.

Alternative options considered:

As an option, the guidance and intervention rate for UKSPF 13 could be maintained as is currently approved. This would mean that there would be less grants provided to businesses overall and that the team would have to continue to liaise with projects over ineligible activity. The proposed changes are to streamline the process and ensure that the opportunity to provide grants to businesses is maximised.

Reason Key: Decision to spend £100,000 or more from an approved budget;

Contact: Neil Johnson, Service Director - Economic Growth Email: neil.johnson@chesterfield.gov.uk Email: neil.johnson@chesterfield.gov.uk Tel: 01246 345241.

Publication date: 05/03/2024

Date of decision: 26/02/2024