The substation requirement was part of the
plans that formed the planning permission granted for the
Enterprise Centre in February 2019 as well as the contract for the
construction of the Enterprise Centre.
Authority delegated to Service Director under G200D "To approve the
siting of electricity sub-stations, gas kiosks and other
installations or equipment of statutory undertakers on Council Land
and to transfer or lease relevant land and grant easements and
rights for that purpose."
Decision type: Non-key
Decision status: For Determination
Notice of proposed decision first published: 03/09/2021
Decision due: 3 Sep 2021 by Service Director - Economic Growth
Contact: Neil Johnson, Service Director - Economic Growth Email: neil.johnson@chesterfield.gov.uk Tel: 01246 345241.